ECI draws upon its vast background in concrete construction, paving, earthwork, railroad construction, and steel fabrication for bridge repairs and construction.
Our completed and on-going projects include:
- North Hero — Grand Isle Draw Bridge Rehabilitation: Replacement of floor beams, steel decking, diaphragms, and lift motor supports
- Vermont Railway Bridge #63, Sunderland, VT: Replacement of superstructure, raised track for new profile, installed new bearings
- Vermont Railway Bridge #214, Pittsford, VT: Replacement of superstructure with precast beams, removed/reinstalled track structure, pointed abutment wall
- Green Mountain Railway Bridges 116 and 120, Chester, VT: Replacement of superstructure with precast beams, removed/reinstalled track structure, pointed abutment wall
- Green Mountain Railway Bridge 114, Rockingham, VT: Replaced 18-ft high backwall for the under-truss bridge using precast T-walls.
- Vermont Railway Bridge 43 Abutment Repairs, Ferrisburgh, VT: Stabilized wing walls with steel sheet piles and tie rods.
- Alburgh Railroad Timber Trestle: Replacement of stringers, caps, and pile posting
- Vermont Railway Bridge #201, Rutland, VT: Replacement of the 45-ft steel superstructure, replacement of the track structure, replacement of backwall with precast concrete elements.
- Numerous Coldplaning/Paving Projects for VTrans (as subcontractor): Rt. 15 - Cambridge, I89 - Montpelier, Mill Street - Bradford, Bridge Street - St Johnsbury, Guptil Road — Waterbury, Main Street — Richford
- Ripton Bridge — Replaced washed-out bridge with cast-in-place abutments and precast post tensioned decking.