Projects
- Hartford Bridge Street Bridge Replacement
- Renewable Energy Project – Vermont National Guard 2.2MW Solar Project
- AllSun Solar Tracker Installations
- East Alburgh Bridge Swing Span Automation
- Whipline Gas Bore
- Gentes Road Bridge Rehabilitation
- CCTA Downtown Transit Center
- Ryegate Culvert Design-Build Replacement Project
- Pittsford Rail Bridge Rehab & Strengthening
- New Haven – Ferrisburg Trenchless Culvert Project
- Franklin County State Airport Expansion – 2024
- Renewable Energy Project – Rock of Ages 100kW Wind Turbine
- Lime Kiln Substation Retaining Wall
- North Hero-Grand Isle Draw Bridge Emergency Superstructure Repairs
- City of Burlington Municipal Paving Contract
- Interstate 91 Rutfill Project
- Pinkham Notch Conduit System
- Grade Crossing at Rte 142 Vernon
- Bellows Falls Tunnel Clearance Improvements
- Burlington Tunnel Emergency Repairs
- VELCO 115kV Underground Electric Transmission Line
- VELCO & GMP Lime Kiln Substations
- VTrans Intelligent Information System (ITS)
- Vermont State Archive Fire Water Storage System
Renewable Energy Project – Vermont National Guard 2.2MW Solar Project
This $8.5M design/build renewable energy project at the Vermont Air National Guard involves about 7,000 individual 230 watt solar panels in three separate systems (solar trackers, roof mount array, and fix array). The majority of the capacity is from the 11 acre fixed array field.
Phase I -The design/build and partial build-out of the 2.2 megawatt solar arrays. The design portion included civil/site layout and details, photovoltaic solar system and electrical, performance data collection and reporting system, inverter and switchgear building, stormwater discharge permit application, and Vermont Public Service Board Rule 5.500 Interconnect Agreement Permit. The site work included around 45,000 cubic yards of earthwork and 15,000 linear feet of conduit. Phase I included 846 KW of solar photovotaliac (PV) panels.
Phase II – This phase added 813 KW of PV solar panels to bring the total output to 1.659 MW allowing for an additional 541 KW for future expansion as funding allows.
The work also involved extensive coordination with the Vermont Air National Guard, the Burlington International Airport, and the Federal Aviation Administration. The project completion date for installing the total 1.659 MW is September 2011.
Subcontractors
GroSolar
Consultants: Krebs & Lansing; Artisan Engineering