Projects
- Hartford Bridge Street Bridge Replacement
- Renewable Energy Project – Vermont National Guard 2.2MW Solar Project
- AllSun Solar Tracker Installations
- East Alburgh Bridge Swing Span Automation
- Whipline Gas Bore
- Gentes Road Bridge Rehabilitation
- CCTA Downtown Transit Center
- Ryegate Culvert Design-Build Replacement Project
- Pittsford Rail Bridge Rehab & Strengthening
- New Haven – Ferrisburg Trenchless Culvert Project
- Renewable Energy Project – Rock of Ages 100kW Wind Turbine
- Lime Kiln Substation Retaining Wall
- North Hero-Grand Isle Draw Bridge Emergency Superstructure Repairs
- City of Burlington Municipal Paving Contract
- Interstate 91 Rutfill Project
- Pinkham Notch Conduit System
- Grade Crossing at Rte 142 Vernon
- Bellows Falls Tunnel Clearance Improvements
- Burlington Tunnel Emergency Repairs
- VELCO 115kV Underground Electric Transmission Line
- VELCO & GMP Lime Kiln Substations
- VTrans Intelligent Information System (ITS)
- Vermont State Archive Fire Water Storage System
Print This Page
Vermont State Archive Fire Water Storage System
ECI Client: DEW Construction
Owner: State of Vermont
Completion Date: 2009
ECI proposed a Design/Built Alternate storage tank for the fire protection system at the Vermont State Archives in Middlesex, VT. The original steel tank option exceeded the owners budget. ECI proposed a 45 x 45 x 6-ft cast-in-place concrete tank built below an existing recreational field. The tank capacity was 80,000 gallons. Special waterproofing and concrete mix designs were used to assure the integrity of the tank.
ECI’s Scope of Work:
- Excavation & Backfill
- Concrete Tank Construction
- Piping & Valve Installation to the Archive Building
- Site Restoration
- Miscellaneous Site Improvements